Giới thiệu về ứng viên

Project Management, Construction Engineering, Quality Control, Materials Testing, Laboratory Management, Supervision Consultancy, Civil Engineering, Monitoring Systems, Infrastructure Projects, Team Leadership, Technical Expertise, Project Coordination …

**PROFILE**
**DINH TUAN HUY**

1. **THE POSITION RECRUITMENT:**
2. **NAME OF COMPANY:**
3. **FULL NAME:**
DINH TUAN HUY
4. **ADDRESS:**
B601 QK7 Block, Trung My Tay Ward, 12 District, HCM City
5. **PHONE NUMBER:**
6. **EMAIL:**
7. **BIRTH YEAR:**
02 October, 1980
Nationality: Viet Nam
8. **PLACE OF GRADUATION:**
Hanoi University of Mining and Geology
9. **CERTIFICATES:**
– Certificate of Professional Training in Supervision Consultancy
– Certification of Supervision Consultant Practice
– Management of Construction Laboratory
– Testing Methods for Determining the Physic – Mechanical Properties of Concrete and Building Materials

10. **WORKPLACE:**
Viet Nam
11. **LANGUAGE:**
| Language | Speaking | Reading | Writing |
|———-|———-|———|———|
| Viet Nam | Native
| English | Medium | Medium | Medium |

12. **WORK EXPERIENCE:**
– **From:** 07/2013 to Present
**COMPANY:** THEHEGEO
**POSITION:** Vice Director

– **From:** 08/2005 to 05/2013
**COMPANY:** Quality Couriers International
**POSITION:** Supervisor – Material Engineer

– **From:** 09/2002 to 08/2005
**COMPANY:** COMATEC SJC
**POSITION:** Site Chief Laboratory

13. **WORK CHARACTERISTICS AND IMPLEMENTATION TASKS:**
1. **Name of Project:** Metro Line 1 – Package CP1A
– **Time Work:** From 10/2016 to Present
– **Location:** Ho Chi Minh City
– **Employer:** Management Authority for Urban Railways (MAUR)
– **Project Description:** Installed monitoring equipment during construction for Ben Thanh railway.
– **Position:** Project Manager, Vice Director of THEHEGEO

2. **Name of Project:** Vam Cong Bridge Construction Project
– **Time Work:** 10/2013 to Present
– **Location:** Dong Thap Province – Can Tho City
– **Employer:** CIPM
– **Project Description:** Established site laboratory, installed equipment for Bridge Health Monitoring System during construction and operation.
– **Position:** Project Manager, Vice Director of THEHEGEO

3. **Name of Project:** Kenh Cut Bridge Construction Project
– **Time Work:** 03/2016 to 11/2017
– **Location:** Cao Lanh City – Dong Thap Province
– **Employer:** Project Management Unit No 6
– **Project Description:** Established site laboratory, testing materials, testing bored pile.
– **Position:** Project Manager, Vice Director of THEHEGEO

4. **Name of Project:** Thái Sơn Long An Residential
– **Time Work:** 10/2015 to 06/2017
– **Location:** Long An
– **Employer:** Cho Lon Sewing Company
– **Project Description:** Established site laboratory, testing materials, testing bored pile.
– **Position:** Project Manager, Vice Director of THEHEGEO

5. **Name of Project:** Rach Lang Bridge Construction Project
– **Time Work:** 08/2015 to 06/2018
– **Location:** Ho Chi Minh City
– **Employer:** HCM Department of Transport
– **Project Description:** Established site laboratory, testing materials, testing bored pile.
– **Position:** Project Manager, Vice Director of THEHEGEO

6. **Name of Project:** Vietnam Central Mekong Delta Connectivity Project
– **Time Work:** 08/2014 to 08/2017
– **Location:** Dong Thap Province
– **Employer:** CIPM
– **Project Description:** Monitoring on soft soil.
– **Position:** Project Manager, Vice Director of THEHEGEO

7. **Name of Project:** Hòa Lạc Hòa Bình Freeway Construction Project
– **Time Work:** 04/2011 to 06/2013
– **Location:** Hanoi Capital to Hoa Binh Province
– **Employer:** GELEXIMCO
– **Project Description:** Construction of freeway.
– **Position:** Materials Engineer, Quality Control, Management of all laboratory in project

8. **Name of Project:** Hồ Chí Minh Road Construction Project
– **Time Work:** 09/2009 to 04/2011
– **Location:** Binh Duong Province – Binh Phuoc Province
– **Employer:** PMU Ho Chi Minh
– **Project Description:** Construction of road.
– **Position:** Materials Engineer, Quality Control, Management of all laboratory in project

9. **Name of Project:** Hồ Chí Minh – Trung Lương Freeway Construction Project
– **Time Work:** 03/2007 to 08/2009
– **Location:** Ho Chi Minh City – Tien Giang Province
– **Employer:** CIPM
– **Project Description:** Construction of freeway.
– **Position:** Materials Engineer, Quality Control, Management of all laboratory in project

10. **Name of Project:** Cau Gie – Ninh Binh Freeway Construction Project
– **Time Work:** 08/2006 to 03/2007
– **Location:** Hanoi Capital – Ninh Binh Province
– **Employer:** VEC
– **Project Description:** Construction of freeway.
– **Position:** Materials Engineer, Quality Control, Management of all laboratory in project

11. **Name of Project:** Hồ Chí Minh Road Construction Project
– **Time Work:** 09/2004 to 08/2006
– **Location:** Hoa Binh Province – Thanh Hoa Province
– **Employer:** PMU Ho Chi Minh
– **Project Description:** Construction of road.
– **Position:** Chief Site Laboratory

12. **Name of Project:** 10 Railway Bridge Construction Project
– **Time Work:** 12/2002 to 09/2004
– **Location:** Quang Tri Province – Phu Yen Province
– **Employer:** PMU 85
– **Project Description:** Construction of bridge and approach road of railway.
– **Position:** Chief Site Laboratory

**CONFIRM**
I, the undersigned, hereby commit:
(i) All the above information is true
(ii) I am solely responsible for the above statements

**DATE:**
15 05 2019
**Signature of Expert:**
**Full Name:** Dinh Tuan Huy